Kalbajar–Lachin Highway
Roadbed construction on the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway.
Key figures
37.8 km
road section
1,975,807
m³ of excavation
34,230
m³ of fill
We are successfully progressing the construction of the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway. Roadbed construction on the km 38+200 – km 47+700 section is currently being carried out by our team.
From August 2022 to the end of December 2024 we completed the works listed below, and construction is still ongoing:
| Type of work | Volume |
|---|---|
| Topsoil stripping | 27,733 m³ |
| Excavation | 1,975,807 m³ |
| Excavation with hydraulic breakers | 2,181 m³ |
| Filling works | 30,416 m³ |
| Rock fill | 3,814 m³ |
Carried out in mountainous terrain, these works include stepped excavation of slopes, breaking of hard rock with hydraulic breakers and filling to design grade.
The project is scheduled for completion in 2026.