Kalbajar–Lachin Highway
Roadbed construction on the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway.
Key figures
37.8 km
road section
1,975,807
m³ of excavation
34,230
m³ of fill
We are successfully progressing the construction of the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway. Roadbed construction on the km 38+200 – km 47+700 section is currently being carried out by our team.
From August 2022 to the end of December 2024 we completed the works listed below, and construction is still ongoing:
| Type of work | Volume |
|---|---|
| Topsoil stripping | 27,733 m³ |
| Excavation | 1,975,807 m³ |
| Excavation with hydraulic breakers | 2,181 m³ |
| Filling works | 30,416 m³ |
| Rock fill | 3,814 m³ |
Carried out in mountainous terrain, these works include stepped excavation of slopes, breaking of hard rock with hydraulic breakers and filling to design grade.