All projects
Ongoing

Kalbajar–Lachin Highway

Roadbed construction on the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway.

Period
2022 – present
Location
Kalbajar – Lachin

Key figures

37.8 km

road section

1,975,807

m³ of excavation

34,230

m³ of fill

We are successfully progressing the construction of the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway. Roadbed construction on the km 38+200 – km 47+700 section is currently being carried out by our team.

From August 2022 to the end of December 2024 we completed the works listed below, and construction is still ongoing:

Type of workVolume
Topsoil stripping27,733 m³
Excavation1,975,807 m³
Excavation with hydraulic breakers2,181 m³
Filling works30,416 m³
Rock fill3,814 m³

Carried out in mountainous terrain, these works include stepped excavation of slopes, breaking of hard rock with hydraulic breakers and filling to design grade.