Kalbajar–Lachin Highway

Roadbed construction on the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway.

Period
2022 – 2026 (ongoing)
Location
Kalbajar – Lachin

Key figures

37.8 km

road section

1,975,807

m³ of excavation

34,230

m³ of fill

We are successfully progressing the construction of the km 35+000 – km 72+800 section of the Kalbajar–Lachin highway. Roadbed construction on the km 38+200 – km 47+700 section is currently being carried out by our team.

From August 2022 to the end of December 2024 we completed the works listed below, and construction is still ongoing:

Type of workVolume
Topsoil stripping27,733 m³
Excavation1,975,807 m³
Excavation with hydraulic breakers2,181 m³
Filling works30,416 m³
Rock fill3,814 m³

Carried out in mountainous terrain, these works include stepped excavation of slopes, breaking of hard rock with hydraulic breakers and filling to design grade.

The project is scheduled for completion in 2026.