Lachin International Airport
Roadbed (earthbed) construction on the km 1+620 – km 3+920 section of the airport — a delivered project.
Key figures
9,982,175
m³ excavated and hauled
1,307,003
m³ of fill
125,253
m³ of rock excavation
The earthbed construction works (topsoil stripping, excavation, filling) on the km 1+620 – km 3+920 section of Lachin International Airport were carried out by A-A MMC and successfully delivered.
Works completed between April 2022 and December 2024, in full compliance with the technology:
| Type of work | Volume |
|---|---|
| Topsoil stripped and stockpiled for reuse | 116,999.8 m³ |
| Benched, stepped excavation, hauling and spreading of ground | 9,982,175 m³ |
| Rock broken with hydraulic breakers, excavated and hauled | 125,253 m³ |
| Fill material hauled from the quarry, spread and compacted | 253,047 m³ |
| Suitable excavated material returned as backfill, spread and compacted | 1,053,956 m³ |
With a total of nearly 10 million m³ of earthworks, the project was delivered in December 2024.