All projects
Delivered

Lachin International Airport

Roadbed (earthbed) construction on the km 1+620 – km 3+920 section of the airport — a delivered project.

Period
2022 – 2024
Location
Lachin

Key figures

9,982,175

m³ excavated and hauled

1,307,003

m³ of fill

125,253

m³ of rock excavation

The earthbed construction works (topsoil stripping, excavation, filling) on the km 1+620 – km 3+920 section of Lachin International Airport were carried out by A-A MMC and successfully delivered.

Works completed between April 2022 and December 2024, in full compliance with the technology:

Type of workVolume
Topsoil stripped and stockpiled for reuse116,999.8 m³
Benched, stepped excavation, hauling and spreading of ground9,982,175 m³
Rock broken with hydraulic breakers, excavated and hauled125,253 m³
Fill material hauled from the quarry, spread and compacted253,047 m³
Suitable excavated material returned as backfill, spread and compacted1,053,956 m³

With a total of nearly 10 million m³ of earthworks, the project was delivered in December 2024.